As a specialized logistics service provider in the wind energy sector, WinTrans Logistics successfully completed the full-scope transportation for a key renewable energy project in Vietnam's Central Highlands — the Ia Pech 2×49.5MW Wind Farm.

Using semi-modular trailers (hydraulic axle lines) , we transported 45 wind turbine blades, each measuring 80.2 meters in length, from the contractor's yard safely to the project site. Every operation accounted for complex road conditions and precise maneuvering to ensure accurate delivery.

Key cargo data:

  • Total: 45 blades
  • Length per blade: 80.2 m
  • Root diameter: approx. 3.5–4.0 m
  • Max chord width: approx. 4.5 m
  • Weight per blade: approx. 22–25 tons

All cargo was delivered on time, in perfect condition, and in full quantity. This project stands as a solid achievement in the field of heavy and oversized logistics.